Introduction
This policy will detail the process to process Operational AARs in the MILPACS System.
Life Cycle Process
This section will detail how to process an AAR.
Step 1
Once an AAR is posted, the first step is to add it to the “Operations” tab. Right click on Row 3 and press “insert 1 above”.
Image 1.
Step 2
Next type the campaign name(if applicable) and Operation name into the C and D column respectively. It is key to note: do not write “Operation” or “campaign” in the C or D column.
Step 3
Add the AAR link into the H column, date of the mission into the F column and the AO into the G column.
Step 4
Bark “awaiting thread lock in the A column. Examples:
Image 2.
Step 5
Once 7 days has passed since the Operation was ran, column E will turn green, this means it’s ready to process, we wait 7 days so that the OIC has enough time to update the master list.
Step 6
Lock the AAR thread.
Image 4.
Step 7
Comment “LOCKED” on the AAR post.
Step 8
Mark column “A” as Awaiting MILPACS.
Image 5.
Step 9
Move to the “Troopers” tab, right click on the “L” column and select “Insert 1 left”.
Image 6.
Step 10
Type the Operation name in row 1, column L and copy/paste the formula from row 4 column M into Row 4 Column L.
Image 7.