Richards.D (talk | contribs) (Created page with "{{DocRelInfo<br />|articlenumber = 7CAV-DR-006<br />|scope = S1 Operations - Life Cycle of an AAR<br />|version = Version 1.0<br />|effectivedate = 21MAR21 |lastmodified...") |
StetchkovA (talk | contribs) |
||
(12 intermediate revisions by one other user not shown) | |||
Line 1: | Line 1: | ||
− | {{DocRelInfo | + | {{DocRelInfo |
+ | |articlenumber = 7CAV-DR-006 | ||
+ | |scope = S1 Operations - Life Cycle of an After action report | ||
+ | |version = Version 1.0 | ||
+ | |effectivedate = 21MAR21 | ||
+ | |lastmodifieddate = 21MAR21 | ||
+ | |approvingauthority = S1 Officer in Charge | ||
+ | |pointofcontact = S1 Officer in Charge | ||
+ | }} | ||
− | | | + | =Introduction= |
+ | This policy will detail the process to process Operational AARs in the MILPACS System. | ||
+ | |||
+ | =Life Cycle Process= | ||
+ | This section will detail how to process an AAR. | ||
+ | |||
+ | ==Step 1== | ||
+ | Once an AAR is posted, the first step is to add it to the “Operations” tab. Right click on Row 3 and press “insert 1 above”. | ||
+ | |||
+ | [[File:AAR_LifeCycle_1.png|AAR_LifeCycle_1.png]] | ||
+ | |||
+ | ==Step 2== | ||
+ | Next type the campaign name(if applicable) and Operation name into the C and D column respectively. It is key to note: do not write “Operation” or “campaign” in the C or D column. | ||
+ | |||
+ | ==Step 3== | ||
+ | Add the AAR link into the H column, date of the mission into the F column and the AO into the G column. | ||
+ | |||
+ | [[File:S1operationsaar2.png|AAR_LifeCycle_1.png]] | ||
+ | |||
+ | ==Step 4== | ||
+ | Bark “awaiting thread lock in the A column. Examples: | ||
+ | |||
+ | [[File:S1operationsaar3.png|AAR_LifeCycle_1.png]] | ||
+ | |||
+ | ==Step 5== | ||
+ | Once 7 days has passed since the Operation was ran, column E will turn green, this means it’s ready to process, we wait 7 days so that the 1IC has enough time to update the master list. | ||
+ | |||
+ | ==Step 6== | ||
+ | Lock the AAR thread. | ||
+ | |||
+ | [[File:S1operationsaar4.png|AAR_LifeCycle_1.png]] | ||
+ | |||
+ | ==Step 7== | ||
+ | Comment “LOCKED” on the AAR post. | ||
+ | |||
+ | [[File:S1operationsaar5.png|AAR_LifeCycle_1.png]] | ||
+ | |||
+ | ==Step 8== | ||
+ | Mark column “A” as Awaiting MILPACS. | ||
+ | |||
+ | [[File:S1operationsaar6.png|AAR_LifeCycle_1.png]] | ||
+ | |||
+ | ==Step 9== | ||
+ | Move to the “Troopers” tab, right click on the “L” column and select “Insert 1 left”. | ||
+ | |||
+ | [[File:S1operationsaar7.png|AAR_LifeCycle_1.png]] | ||
+ | |||
+ | ==Step 10== | ||
+ | Type the Operation name in row 1, column L and copy/paste the formula from row 4 column M into Row 4 Column L. | ||
+ | |||
+ | [[File:S1operationsaar8.png|AAR_LifeCycle_1.png]] | ||
+ | |||
+ | The L column should be displayed like this: | ||
+ | * 0 | ||
+ | Ensure that you type the name of the Operation in the same way it’s typed on the “Operations” tab or you will get an Error | ||
+ | |||
+ | ==Step 11== | ||
+ | Move to the “Rank Remover Utility” CTRL+C from the AAR post’s master list, then CTRL+SHIFT+V into row 4 column B | ||
+ | |||
+ | [[File:S1operationsaar9.png|AAR_LifeCycle_1.png]] | ||
+ | |||
+ | * If it shows “format” in the H column, it means the rank is incorrect, the trooper could have been promoted/demoted since then, so try the rank above, if it still shows format, check their MILPACS to see their rank. | ||
+ | |||
+ | [[File:AAR_LifeCycle_9.png|AAR_LifeCycle_1.png]] </br> | ||
+ | [[File:AAR_LifeCycle_10.png|AAR_LifeCycle_1.png]] | ||
+ | |||
+ | ==Step 12== | ||
+ | Ensure that none of the names say “FORMAT” in the H column | ||
+ | |||
+ | ==Step 13== | ||
+ | Transfer the troopers to the Operation builder, there’s a button in the top left of the screen, but sometimes it is not visible: | ||
+ | |||
+ | [[File:S1operationsaar10.png|AAR_LifeCycle_1.png]] | ||
+ | |||
+ | [[File:S1operationsaar11.png|AAR_LifeCycle_1.png]] | ||
+ | |||
+ | * If you left click here it will run the script and this will display at the top of your screen: | ||
+ | |||
+ | [[File:S1operationsaar12.png|AAR_LifeCycle_1.png]] | ||
+ | |||
+ | * This will appear in the bottom right once the script has finished: | ||
+ | |||
+ | [[File:S1operationsaar13.png|AAR_LifeCycle_1.png]] | ||
+ | |||
+ | ==Step 14== | ||
+ | Move to the Operations builder, and make sure all boxes are green: | ||
+ | |||
+ | [[File:S1operationsaar14.png|AAR_LifeCycle_1.png]] | ||
+ | |||
+ | # Check 1: If Check #1 fails that means that the trooper has been entered multiple times on this list. >>Delete<< the rows that are multiples. DO NOT LEAVE ANY GAPS BETWEEN TROOPERS ROWS. | ||
+ | |||
+ | # Check 2: If Check #2 fails then the trooper's name was not found in MILPACS. Check for correct spelling. | ||
+ | |||
+ | # Check 3: If Check #3 fails the trooper needs to be added to the 'Troopers' sheet before running the script. | ||
+ | |||
+ | [[File:S1operationsaar15.png|AAR_LifeCycle_1.png]] | ||
+ | |||
+ | ===How to Add a Trooper=== | ||
+ | * Move to the “Troopers” tab | ||
+ | * Locate the alphabetical position (firstname) that the new trooper must go | ||
+ | * Insert a new row where they must go: | ||
+ | |||
+ | [[File:S1operationsaar16.png|AAR_LifeCycle_1.png]] | ||
+ | |||
+ | * Insert their name into column C, check their MILPACS, if they have any previous Operations attended add the number of Operations into the D column, if they haven't attended any just put ”0”. | ||
+ | * Drag the formula from the E and F column down into the boxes. | ||
+ | * In the “G,H,I and J” column write “0” and ensure all of them are not colored. | ||
+ | |||
+ | [[File:S1operationsaar17.png|AAR_LifeCycle_1.png]] | ||
+ | |||
+ | * If the person has been awarded a service ribbon in the past, colour one of the sections green relative to the medal they have been awarded. | ||
+ | |||
+ | [[File:S1operationsaar18.png|AAR_LifeCycle_1.png]] | ||
+ | |||
+ | ==Step 15== | ||
+ | Once all checks are green, select the Operation you are processing from the drop down menu and press the button at the top(this can also appear as invisible but it is located here: | ||
+ | |||
+ | [[File:S1operationsaar19.png|AAR_LifeCycle_1.png]] | ||
+ | [[File:S1operationsaar20.png|AAR_LifeCycle_1.png]] | ||
+ | |||
+ | ==Step 16== | ||
+ | Check that troopers were added to the sheet: | ||
+ | |||
+ | [[File:S1operationsaar21.png|AAR_LifeCycle_1.png]] | ||
+ | |||
+ | * To do this, move to the “Troopers” tab and check that it says “MILPACS” in the L column in at least one row. | ||
+ | |||
+ | [[File:S1operationsaar22.png|AAR_LifeCycle_1.png]] | ||
+ | |||
+ | ==Step 17== | ||
+ | Move to the “MILPACS Helper” tab and select the Operation you are processing at the Top. | ||
+ | |||
+ | [[File:S1operationsaar23.png|AAR_LifeCycle_1.png]] | ||
+ | |||
+ | |||
+ | ==Step 18== | ||
+ | Add the Op to MILPACS. | ||
+ | * Copy the verbage | ||
+ | * Press the right hand link of that row | ||
+ | * Paste the verbage | ||
+ | * Change the Roster type to “Operation” | ||
+ | * Change the Record date to the date of the OP | ||
+ | * Press save | ||
+ | |||
+ | [[File:S1operationsaar24.png|AAR_LifeCycle_1.png]] | ||
+ | |||
+ | ==Step 19== | ||
+ | Once all the troopers are complete, go to the “Troopers tab” in the top where it says “S1 Tools” go to “MILPACS>complete” then “Complete L column”: | ||
+ | |||
+ | [[File:S1operationsaar25.png|AAR_LifeCycle_1.png]] | ||
+ | |||
+ | ==Step 20== | ||
+ | Go to the “Operations” tab and change the status to “Complete”: | ||
+ | |||
+ | [[File:S1operationsaar26.png|AAR_LifeCycle_1.png]] | ||
+ | |||
+ | ==Step 21== | ||
+ | Ensure the troops tab is displaying Operation attendance: | ||
+ | |||
+ | [[File:S1operationsaar27.png|AAR_LifeCycle_1.png]] | ||
+ | |||
+ | ==Step 22== | ||
+ | Comment on the AAR post “S1 Operations Updated”. | ||
+ | |||
+ | [[File:S1operationsaar28.png|AAR_LifeCycle_1.png]] | ||
+ | |||
+ | ==Step 23== | ||
+ | Add your name into the “processed by” column on the Operations tab. You have successfully processed an operation. |
Latest revision as of 12:23, 18 June 2023
This is the Document Release Information | |
Article Number: | 7CAV-DR-006 |
Scope: | S1 Operations - Life Cycle of an After action report |
Version: | Version 1.0 |
Effective Date: | 21MAR21 |
Last Modified Date: | 21MAR21 |
Approving Authority: | S1 Officer in Charge |
Point of Contact: | S1 Officer in Charge |
Introduction
This policy will detail the process to process Operational AARs in the MILPACS System.
Life Cycle Process
This section will detail how to process an AAR.
Step 1
Once an AAR is posted, the first step is to add it to the “Operations” tab. Right click on Row 3 and press “insert 1 above”.
Step 2
Next type the campaign name(if applicable) and Operation name into the C and D column respectively. It is key to note: do not write “Operation” or “campaign” in the C or D column.
Step 3
Add the AAR link into the H column, date of the mission into the F column and the AO into the G column.
Step 4
Bark “awaiting thread lock in the A column. Examples:
Step 5
Once 7 days has passed since the Operation was ran, column E will turn green, this means it’s ready to process, we wait 7 days so that the 1IC has enough time to update the master list.
Step 6
Lock the AAR thread.
Step 7
Comment “LOCKED” on the AAR post.
Step 8
Mark column “A” as Awaiting MILPACS.
Step 9
Move to the “Troopers” tab, right click on the “L” column and select “Insert 1 left”.
Step 10
Type the Operation name in row 1, column L and copy/paste the formula from row 4 column M into Row 4 Column L.
The L column should be displayed like this:
- 0
Ensure that you type the name of the Operation in the same way it’s typed on the “Operations” tab or you will get an Error
Step 11
Move to the “Rank Remover Utility” CTRL+C from the AAR post’s master list, then CTRL+SHIFT+V into row 4 column B
- If it shows “format” in the H column, it means the rank is incorrect, the trooper could have been promoted/demoted since then, so try the rank above, if it still shows format, check their MILPACS to see their rank.
Step 12
Ensure that none of the names say “FORMAT” in the H column
Step 13
Transfer the troopers to the Operation builder, there’s a button in the top left of the screen, but sometimes it is not visible:
- If you left click here it will run the script and this will display at the top of your screen:
- This will appear in the bottom right once the script has finished:
Step 14
Move to the Operations builder, and make sure all boxes are green:
- Check 1: If Check #1 fails that means that the trooper has been entered multiple times on this list. >>Delete<< the rows that are multiples. DO NOT LEAVE ANY GAPS BETWEEN TROOPERS ROWS.
- Check 2: If Check #2 fails then the trooper's name was not found in MILPACS. Check for correct spelling.
- Check 3: If Check #3 fails the trooper needs to be added to the 'Troopers' sheet before running the script.
How to Add a Trooper
- Move to the “Troopers” tab
- Locate the alphabetical position (firstname) that the new trooper must go
- Insert a new row where they must go:
- Insert their name into column C, check their MILPACS, if they have any previous Operations attended add the number of Operations into the D column, if they haven't attended any just put ”0”.
- Drag the formula from the E and F column down into the boxes.
- In the “G,H,I and J” column write “0” and ensure all of them are not colored.
- If the person has been awarded a service ribbon in the past, colour one of the sections green relative to the medal they have been awarded.
Step 15
Once all checks are green, select the Operation you are processing from the drop down menu and press the button at the top(this can also appear as invisible but it is located here:
Step 16
Check that troopers were added to the sheet:
- To do this, move to the “Troopers” tab and check that it says “MILPACS” in the L column in at least one row.
Step 17
Move to the “MILPACS Helper” tab and select the Operation you are processing at the Top.
Step 18
Add the Op to MILPACS.
- Copy the verbage
- Press the right hand link of that row
- Paste the verbage
- Change the Roster type to “Operation”
- Change the Record date to the date of the OP
- Press save
Step 19
Once all the troopers are complete, go to the “Troopers tab” in the top where it says “S1 Tools” go to “MILPACS>complete” then “Complete L column”:
Step 20
Go to the “Operations” tab and change the status to “Complete”:
Step 21
Ensure the troops tab is displaying Operation attendance:
Step 22
Comment on the AAR post “S1 Operations Updated”.
Step 23
Add your name into the “processed by” column on the Operations tab. You have successfully processed an operation.